A. Construction/Installation Inspection.

1. All projects permitted or approved by the utility under a utility developer extension agreement or other permit are subject to utility inspection to ensure compliance with the code and permit/approval conditions. As a condition of permit issuance or execution of a utility developer extension agreement, the property owner shall consent to inspection and testing.

2. Newly installed water facilities shall be inspected, tested, and documentation completed according to the permit requirements or developer extension agreement conditions, the engineering standards, and procedures.

3. Newly installed or relocated backflow prevention assemblies shall be inspected, tested, and certified pursuant to the requirements of BCC 24.02.190(D).

4. The quality, taste and odor of water drawn from new water mains shall be the same as the quality, taste and odor of water in the existing facility classed as acceptable for use by the utility. Should the water not be acceptable in quality, taste or odor, required steps as approved by the utility shall be taken to attain acceptable water quality standards.

B. Warranty Inspections and Tests. Facilities and equipment accepted by the utility under specific warranties may be reinspected at the utility’s discretion and, if necessary, retested prior to the expiration of the warranty period. (Ord. 5963 § 1, 2010.)