This section is included in your selections.

Modifications to geologic hazard critical areas and critical area buffers shall only be approved if the Director determines that the modification:

A. Will not increase the threat of the geological hazard to adjacent properties over conditions that would exist if the provisions of this part were not modified;

B. Will not adversely impact other critical areas;

C. Is designed so that the hazard to the project is eliminated or mitigated to a level equal to or less than would exist if the provisions of this part were not modified;

D. Is certified as safe as designed and under anticipated conditions by a qualified engineer or geologist, licensed in the state of Washington;

E. The applicant provides a geotechnical report prepared by a qualified professional demonstrating that modification of the critical area or critical area buffer will have no adverse impacts on stability of any adjacent slopes, and will not impact stability of any existing structures. Geotechnical reporting standards shall comply with requirements developed by the Director in City of Bellevue Submittal Requirements Sheet 25, Geotechnical Report and Stability Analysis Requirements, now or as hereafter amended;

F. Any modification complies with recommendations of the geotechnical support with respect to best management practices, construction techniques or other recommendations; and

G. The proposed modification to the critical area or critical area buffer with any associated mitigation does not significantly impact habitat associated with species of local importance, or such habitat that could reasonably be expected to exist during the anticipated life of the development proposal if the area were regulated under this part. (Ord. 5680, 6-26-06, § 3)