A. Construction/Installation Inspection.

1. All projects permitted or approved by the utility under a utility developer extension agreement or other permit are subject to utility inspection to ensure compliance with the code and permit/approval conditions. As a condition of permit issuance or execution of a utility developer extension agreement, the property owner shall consent to inspection and testing.

2. Newly installed sewer facilities shall be inspected, tested, and documentation completed according to the permit requirements or developer extension agreement conditions, the engineering standards, and procedures.

B. Warranty Inspections and Tests. Facilities and equipment accepted by the utility under specific warranties may be reinspected at the utility’s discretion and, if necessary, retested prior to the expiration of the warranty period. (Ord. 5964 § 1, 2010.)